What is the Major Works Renewal Programme?
The City of London Corporation is investing £105 million in repairing and upgrading the Golden Lane Estate. The programme covers windows, roofing, insulation, ventilation, heating, fire safety, electrical systems and redecoration across all blocks.
The estate was built in the 1950s to a design by Chamberlin, Powell & Bon and every block is listed. Much of the original building fabric, particularly the windows and roofs, is now at the end of its serviceable life. The programme is designed to bring the buildings up to modern standards of safety, warmth and weathertightness while protecting what makes them architecturally significant.
Why are these works needed now?
There are three main reasons why the programme is needed now:
Which blocks are included?
All blocks are included in the major works programme. The scope and timing differ block by block because the buildings have different window types, roof construction, and fire safety issues.
Who is doing the work?
All blocks are included in the major works programme. The scope and timing differ block by block because the buildings have different window types, roof construction, and fire safety issues.
Construction contractors have not yet been appointed for any block. That happens through a competitive tender process, block by block.
When will work start on my block?
The programme runs from now until the mid-2030s. Current indicative dates are:
These dates are indicative and will move as the programme develops. We update them when they change.
Why does this process take so long?
Every block needs planning permission and listed building consent, which takes months. Most blocks are classified as Higher Risk Buildings under the Building Safety Act, which means the works also need approval from the Building Safety Regulator through a process called Gateway 2. The Regulator currently has a significant backlog and its review typically takes around eight to nine months, sometimes longer. Only then can a contractor start.
On top of that, contractors have to be procured through a formal competitive tender, and leaseholders have to be formally consulted about costs under Section 20 of the Landlord and Tenant Act. Neither can be short-circuited.
Why can't the whole estate be done at once?
Practically, it can't be. Decanting residents, managing site logistics and running contracts on nine listed buildings simultaneously isn't deliverable. The current assumption is that two blocks can be decanted at a time, using separate contracts and different contractors.
What is Gateway 2 and why does it matter to me?
Gateway 2 is the stage of the Building Safety Act process where the Building Safety Regulator has to approve the design of works to a Higher Risk Building before construction can begin. It's more rigorous and less flexible than standard building control. It matters to residents for two reasons.
First, it adds close to a year to the programme for every impacted block.
Second, the Regulator have the final say on some design decisions.
Will my home be warmer and cheaper to heat?
This is the intention. The modelled reductions in heating demand are set out in the windows section above.
If you make my flat more airtight, will I get condensation and mould?
Two things reduce the risk. First, testing at 2 Bayer House with the Building Research Establishment shows that even the maximum improvement in airtightness from the window works would leave the building relatively leaky. The change is less dramatic than at Crescent House, where airtightness roughly halved.
Second, and more importantly, every flat is getting a new ventilation system specifically designed to manage moisture. A specific condensation risk analysis is also being carried out.
How does the new ventilation system work?
It is a demand-controlled mechanical extract system, the same approach as Crescent House. In plain terms:
You do not have to operate it. It runs quietly in the background and responds automatically.
What is a Higher Risk Building, and is mine one?
A Higher Risk Building is one over 18 metres or seven storeys, as defined by the Building Safety Act 2022. Works to these buildings need approval from the Building Safety Regulator rather than ordinary building control.
All blocks in the programme are Higher Risk Buildings except Cuthbert Harrowing House, which is smaller and goes through the standard local authority route.
Why do the maisonettes need a suppression system?
Each maisonette has two floors linked by an open internal staircase. Under the original 1950s design, the second escape route from the upper floor was out onto the balcony, across a metal grille, through a small glass panel into the neighbouring flat, and out through your neighbour’s front door.
That is no longer acceptable under current regulations, for two reasons: it depends on escaping through someone else’s home, and it leaves an unprotected internal stair in a two-storey dwelling. Fire risk assessments have flagged it for a number of years. Installing a suppression system inside each maisonette means any fire is controlled quickly, giving you time to escape down your own stair and out of your own front door without relying on the balcony route.
What is mist suppression and how is it different from sprinklers?
Both are automatic fire suppression systems. The difference is scale.
Sprinklers need a large water tank, a backup pump and substantial pipework. Installing them is very disruptive.
Mist suppression uses a small pump set and tank in the basement feeding much smaller pipework to compact heads in each room. It discharges a fine mist rather than a spray, using far less water if it ever activates.
The proposal is mist suppression, on the basis that it does the job with much less impact on your home.
Is my front door being replaced with a fire door?
For most residents, no. In most blocks the communal escape route is well designed, with two staircases and escape possible in both directions along the access corridors, so flat entrance doors do not need upgrading.
Where an upgrade is needed, the door will be replaced.
Will I have to move out of my home?
The programme is currently planned on a worst-case assumption that decanting will be required for each block (apart from possibly Stanley Cohen). But the team is actively working to reduce or avoid it.
If I do have to move, where would I go and for how long?
The current planning assumption is a rolling programme of around six flats or maisonettes at a time, for six to eight weeks each. Residents would be moved to a similar property either on the estate, or nearby.
Two dedicated Resident Decant Officers are being recruited by the City Corporation specifically to support residents through this.
Why is the whole electrical system being replaced?
Inspections have found the main electrical distribution in every block is old, does not comply with current standards, and in places is not working. Because replacing one major component of an old system requires the whole system to be brought up to standard, the scope covers full replacement of the incoming mains to every flat and all associated systems.
What does the electrical work involve?
Is my gas being removed?
At Crescent House, yes. A safety assessment found that gas pipes and meters in communal areas pose a fire risk, so the gas supply will be removed and homes will switch to electric heating and hot water. At Basterfield, Bayer, Bowater, Stanley Cohen, Hatfield and Cullum Welch Houses, no. Gas boilers and their flues will be kept. At Great Arthur House, a full survey of the gas system is under way and a decision will be made once it is complete. For Cuthbert Harrowing House, we will confirm the approach as the design is finalised.
I am a leaseholder. How much will this cost me?
We do not yet know the cost, and we do not want to give an estimate that may later prove inaccurate. Costs will be confirmed once contractors have returned their tender prices.
Leaseholders will be formally notified through the Section 20 consultation process. Stage 1 confirms that works are proposed. Stage 2, once tenders have been received and reviewed, will include the relevant cost information.
What is Section 20 and where are we in the process?
Section 20 of the Landlord and Tenant Act 1985 requires landlords to consult leaseholders before carrying out major works.
Stage 1 is a statutory notice of intention. It is not required to include costs, specifications or drawings. That is standard practice across local authorities and housing associations, though we understand it is frustrating to receive a notice without numbers.
Stage 2 is issued after tenders are returned. It includes the financial information and evidence of market testing, and leaseholders can view the relevant technical and pricing documents under supervised conditions.
For Crescent House, Stage 1 consultation has closed and responses are being worked through. Stage 2 is expected early in 2027, having been moved from autumn 2026 to avoid the process falling over the Christmas period.
For other blocks, Section 20 consultation happens during each block’s tender period. See the Programme Proposals page for indicative timings.
How disruptive will this be day to day?
A major works programme on a listed 1950s estate is disruptive, we are designing to minimise it where we can.
Working hours, noise management, dust control and access arrangements will be set out in the contractor’s method statements once appointed, and shared with residents before work starts.
Can I see the works before they happen to my home?
Yes. Trial works have been carried out in empty flats across the different block types. Open days are being arranged so residents can see the refurbished windows and the ventilation installation in context.
Dates will be published on the Latest News page and circulated by email.
The estate is listed. How does that affect the works?
Significantly. Every block is individually listed, Crescent House at Grade II* and the others at Grade II, which means most external changes need listed building consent as well as planning permission.
That is the main reason the approach is conservation-led. Retaining and repairing original fabric is a principle supported by Historic England, and any proposal to replace rather than repair has to be robustly justified in the listed building application.
Can I object to or comment on a planning application?
Yes. Once an application is submitted it is published by the City of London Corporation’s planning service and anyone can comment during the consultation period. We will flag submission dates on this website and by email.
How do I find out what is happening?
Significantly. Every block is individually listed, Crescent House at Grade II* and the others at Grade II, which means most external changes need listed building consent as well as planning permission.
What are the Resident Liaison Groups and can I join?
We are keen to strengthen attendance, particularly from leaseholders. If you would like to join, please email info@goldenlaneprojects.co.uk.
I have a question that is not answered here.
Please email info@goldenlaneprojects.co.uk. We answer questions in writing and add common ones to this page.
If you have asked something and have not had a reply, please chase us. We would rather know.