This approach is based upon the following assumptions:
- All blocks on the Golden Lane Estate will require decanting (apart from possibly Stanley Cohen) to accommodate window refurbishment
- City of London Corporation can accommodate decanting of 2 blocks at a time using separate contracts and different principal contractors
- Decanting is based upon a rolling programme of 6 flats/maisonettes at a time for a period of 6-8 weeks Works will be delivered as part of competitively tendered packages consisting either of a single block or groups of blocks as indicated below.
Crescent House
Crescent House is being refurbished as part of the Golden Lane Estate Major Works Renewal Programme.
Because the building is over 18 metres tall, it is classified as a Higher Risk Building under the Building Safety Act 2022, meaning the works require approval from the Building Safety Regulator as well as standard planning permission.
The works, which include fire safety upgrades, full electrical replacement, removal of gas, new mechanical ventilation, communal redecorations and building fabric repairs, are designed to keep the building safe, warm and in good condition for the long term.
Planning permission and listed building consent have already been obtained for the window refurbishment and roof works. Because the works require planning permission and other formal approvals, some details are not yet finalised and may still change. The contractor will mobilise in January 2028. Construction is expected to start on site in Spring/Summer 2028 and complete in October 2031.
All residents will need to temporarily move to alternative accommodation while works are carried out. Residents will be moved to a similar flat and kept informed well in advance.
Estimated works
Dates
Design and approvals: planning and listed building consent
Feb 2025 – Jul 2026 Fire doors: TBD
Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)
Jul 2026 – Jan 2027
Design and approvals: Building Regulations sign-off (Gateway 2)
Jan 2027 – Dec 2027
Contractor prepares to start on site
Jan 2028 – Mar 2028
Construction works on site
Spring/Summer 2028 - Oct 2031
Residents begin moving to temporary accommodation
Jul 2028
Cuthbert Harrowing House
Cuthbert Harrowing House is being refurbished as part of the Golden Lane Estate Major Works Renewal Programme.
The proposed works include window refurbishment, mechanical ventilation, fire safety systems, roof replacement, electrical upgrades, removal of gas and general building fabric repairs.
As the works require planning permission and other formal approvals, some elements remain subject to consultation and may still change.
The contractor will mobilise in February 2028. Construction is expected to start on site in Spring/Summer 2028 and complete in Summer/Autumn 2029. Residents will need to move to temporary accommodation while works are carried out in their part of the building.
Estimated works
Dates
Informal resident consultation event
May 2026
Resident consultation on proposed planning and listed building application
July 2026
Planning application submitted
January 2027
Planning and listed building consent decision expected
Spring 2027
Tender process (including Section 20 consultation with leaseholders)
[TBC: dates shift after the planning decision]
Contractor mobilisation
February 2028
Construction works commence
Spring/Summer 2028
Construction works complete
Summer/Autumn 2029
Great Arthur House
The original design of the 1950s roof [confirm] is being reviewed and to be reinstated where possible to showcase its iconic design. The project comprises of renovating its distinctive canopy, pond and Japanese roof garden. Scope also includes improvements to the roof’s watertightness and insulation.
Progress is being made on the design phase of the Great Arthur House works, including the roof. [wording to confirm]
Originally planned as a standalone contract, the roof refurbishment will now be integrated into the wider programme of building improvements for Great Arthur House enabling a more coordinated and efficient approach to project delivery. Design development is underway with an application for Planning and Listed Building Consent to follow. The proposals include the reinstatement of the Japanese roof garden, alongside a range of other improvements.
Estimated works
Dates
Surveys, investigations and design work
2025–2026
Design and approvals: planning consent (Gateway 1): this is likely to be done as two separate applications, the first for the roof and the second for all the internal works
Oct 2026 – April
2027
Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)
May 2027 – Dec
2027
Building Safety Regulator approval (Gateway 2) — required before construction can begin
Dec 2027 – Dec
2028
Contractor prepares to start on site
Jan 2029 – April
2029
Construction works on site
May 2029 – May
2032
Construction works complete
May 2032
Basterfield, Bayer, Bowater and Stanley Cohen Houses
These four blocks are being refurbished together as a single programme (Phase 2C) as part of the Golden Lane Estate Major Works Renewal Programme.
All four buildings are classed as Higher Risk Buildings under the Building Safety Act 2022, meaning the works require approval from the Building Safety Regulator as well as standard planning permission.
The proposed works include window refurbishment, mechanical ventilation, fire safety upgrades, full electrical replacement, roof replacement, removal of gas and building fabric repairs. Some details are not yet finalised and may still change. Construction is expected to start on site in February 2032 and complete in September 2035. Residents will need to move to temporary accommodation while works are carried out.
Estimated works
Dates
Fire safety surveys and reports, including an assessment of the external walls and a review of fire risk across the building
Aug 2025 – Nov 2025
Design and approvals: planning and listed building consent
Apr 2026 – Dec 2027
Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)
Jun 2028 – Dec 2029
Building Safety Regulator approval (Gateway 2) — required before construction can begin
Jun 2030 – Jun 2031
Contractor prepares to start on site
Jul 2031 – Nov 2031
Construction works on site
Feb 2032 - Sept 2035
Construction works complete
September 2035
Hatfield House and Cullum Welch House
Hatfield House and Cullum Welch House are being refurbished together as a single programme (Phase 2D) as part of the Golden Lane Estate Major Works Renewal Programme.
Both buildings are classed as Higher Risk Buildings under the Building Safety Act 2022, meaning the works require approval from the Building Safety Regulator as well as standard planning permission.
The proposed works include window refurbishment, mechanical ventilation, fire safety upgrades, full electrical replacement, roof replacement, removal of gas and building fabric repairs.
Some details are not yet finalised and may still change. Construction is expected to start on site in May 2032 and complete in October 2035.
Estimated works
Dates
Fire safety surveys and reports, including an assessment of the external walls and a review of fire risk across the building
Sep 2025 – Sep 2026
Design and approvals: planning and listed building consent
Mar 2028 – Nov 2029
Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)
May 2030 – Jan 2031
Building Safety Regulator approval (Gateway 2) — required before construction can begin
Mar 2031 – Nov 2031
Contractor prepares to start on site
Nov 2031 – Apr 2032
Construction works on site
May 2032 – Oct 2035
Construction works complete
October 2035