The Investment Programme

Indicative Timeline 2025–2035

This approach is based upon the following assumptions:

Crescent House

Crescent House is being refurbished as part of the Golden Lane Estate Major Works Renewal Programme.

Because the building is over 18 metres tall, it is classified as a Higher Risk Building under the Building Safety Act 2022, meaning the works require approval from the Building Safety Regulator as well as standard planning permission.

The works, which include fire safety upgrades, full electrical replacement, removal of gas, new mechanical ventilation, communal redecorations and building fabric repairs, are designed to keep the building safe, warm and in good condition for the long term.

Planning permission and listed building consent have already been obtained for the window refurbishment and roof works. Because the works require planning permission and other formal approvals, some details are not yet finalised and may still change. The contractor will mobilise in January 2028. Construction is expected to start on site in Spring/Summer 2028 and complete in October 2031.

All residents will need to temporarily move to alternative accommodation while works are carried out. Residents will be moved to a similar flat and kept informed well in advance.

Estimated works

Dates

Design and approvals: planning and listed building consent

Feb 2025 – Jul 2026 Fire doors: TBD

Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)

Jul 2026 – Jan 2027

Design and approvals: Building Regulations sign-off (Gateway 2)

Jan 2027 – Dec 2027

Contractor prepares to start on site

Jan 2028 – Mar 2028

Construction works on site

Spring/Summer 2028 - Oct 2031

Residents begin moving to temporary accommodation

Jul 2028

Cuthbert Harrowing House

Cuthbert Harrowing House is being refurbished as part of the Golden Lane Estate Major Works Renewal Programme.

The proposed works include window refurbishment, mechanical ventilation, fire safety systems, roof replacement, electrical upgrades, removal of gas and general building fabric repairs.

As the works require planning permission and other formal approvals, some elements remain subject to consultation and may still change.

The contractor will mobilise in February 2028. Construction is expected to start on site in Spring/Summer 2028 and complete in Summer/Autumn 2029. Residents will need to move to temporary accommodation while works are carried out in their part of the building.

Estimated works

Dates

Informal resident consultation event

May 2026

Resident consultation on proposed planning and listed building application

July 2026

Planning application submitted

January 2027

Planning and listed building consent decision expected

Spring 2027

Tender process (including Section 20 consultation with leaseholders)

[TBC: dates shift after the planning decision]

Contractor mobilisation

February 2028

Construction works commence

Spring/Summer 2028

Construction works complete

Summer/Autumn 2029

Great Arthur House

The original design of the 1950s roof [confirm] is being reviewed and to be reinstated where possible to showcase its iconic design. The project comprises of renovating its distinctive canopy, pond and Japanese roof garden. Scope also includes improvements to the roof’s watertightness and insulation.

Progress is being made on the design phase of the Great Arthur House works, including the roof. [wording to confirm]

Originally planned as a standalone contract, the roof refurbishment will now be integrated into the wider programme of building improvements for Great Arthur House enabling a more coordinated and efficient approach to project delivery. Design development is underway with an application for Planning and Listed Building Consent to follow. The proposals include the reinstatement of the Japanese roof garden, alongside a range of other improvements.

Estimated works

Dates

Surveys, investigations and design work

2025–2026

Design and approvals: planning consent (Gateway 1): this is likely to be done as two separate applications, the first for the roof and the second for all the internal works

Oct 2026 – April 2027

Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)

May 2027 – Dec 2027

Building Safety Regulator approval (Gateway 2) — required before construction can begin

Dec 2027 – Dec 2028

Contractor prepares to start on site

Jan 2029 – April 2029

Construction works on site

May 2029 – May 2032

Construction works complete

May 2032

Basterfield, Bayer, Bowater and Stanley Cohen Houses

These four blocks are being refurbished together as a single programme (Phase 2C) as part of the Golden Lane Estate Major Works Renewal Programme.

All four buildings are classed as Higher Risk Buildings under the Building Safety Act 2022, meaning the works require approval from the Building Safety Regulator as well as standard planning permission.

The proposed works include window refurbishment, mechanical ventilation, fire safety upgrades, full electrical replacement, roof replacement, removal of gas and building fabric repairs. Some details are not yet finalised and may still change. Construction is expected to start on site in February 2032 and complete in September 2035. Residents will need to move to temporary accommodation while works are carried out.

Estimated works

Dates

Fire safety surveys and reports, including an assessment of the external walls and a review of fire risk across the building

Aug 2025 – Nov 2025

Design and approvals: planning and listed building consent

Apr 2026 – Dec 2027

Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)

Jun 2028 – Dec 2029

Building Safety Regulator approval (Gateway 2) — required before construction can begin

Jun 2030 – Jun 2031

Contractor prepares to start on site

Jul 2031 – Nov 2031

Construction works on site

Feb 2032 - Sept 2035

Construction works complete

September 2035

Hatfield House and Cullum Welch House

Hatfield House and Cullum Welch House are being refurbished together as a single programme (Phase 2D) as part of the Golden Lane Estate Major Works Renewal Programme.

Both buildings are classed as Higher Risk Buildings under the Building Safety Act 2022, meaning the works require approval from the Building Safety Regulator as well as standard planning permission.

The proposed works include window refurbishment, mechanical ventilation, fire safety upgrades, full electrical replacement, roof replacement, removal of gas and building fabric repairs.

Some details are not yet finalised and may still change. Construction is expected to start on site in May 2032 and complete in October 2035.

Estimated works

Dates

Fire safety surveys and reports, including an assessment of the external walls and a review of fire risk across the building

Sep 2025 – Sep 2026

Design and approvals: planning and listed building consent

Mar 2028 – Nov 2029

Tender process, finding and appointing a contractor (including statutory consultation with leaseholders about costs)

May 2030 – Jan 2031

Building Safety Regulator approval (Gateway 2) — required before construction can begin

Mar 2031 – Nov 2031

Contractor prepares to start on site

Nov 2031 – Apr 2032

Construction works on site

May 2032 – Oct 2035

Construction works complete

October 2035